I-69 Southwest Freeway will close southbound from June 6 to June 9 for Phase Two of the Brazos River Bridge project.
HOUSTON — I-69 Southwest Freeway will be closed southbound from University Boulevard to Greatwood Parkway starting 9 p.m., June 6 until 5 a.m., June 9.
This closure is a part of ongoing construction and the start of Phase Two of the I-69 Brazos River Bridge project.
Texas Department of Transportation says all southbound traffic will split around the work zone. The three southbound lanes will shift right onto a new bridge. The HOV lane and one main lane will shift to the left.
Northbound lanes will not be affected during this part of the construction.
According to TxDOT, the $53 million project will extend the I-69 main lane and frontage roads north and southbound around 1,000 feet. The project will also permanently remove the damaged turnaround under the bridge. Completion is targeted for late 2027.